Park Project - Anthony Skarratt Reserve (Stage 1)

  • Project typeNew
  • Project scheduleMarch 2026 Completion (Weather Permitting)

Subscribe at the bottom of this page to stay updated via email.

The Hills Shire Council has awarded the contract for the delivery of Stage 1 of Anthony Skarratt Reserve, Box Hill.

Stage 1 work includes:

  • A new Community Centre
  • A satellite library
  • A youth playground and plaza
  • A playgroup space with outdoor play area
  • Carparking for 187 spaces
  • Landscaping work
  • Installation of fencing and boundary division wall
  • A roundabout at Nelson Road, Box Road and the access driveway into the facility
  • Localised pavement widening on Nelson Road incorporating a new bus bay fronting the reserve
  • Adjustments to existing service utilities including Telstra, NBN, Sydney Water and electrical services
  • Upgraded stormwater infrastructure
  • Construction traffic management and controls

Work will generally be carried out Monday - Saturday from 7am to 5pm, however some night work may also be necessary to minimise impact on peak hour traffic flow. Night works may also be required to deliver heavy vehicle plant machinery, and for service utility relocation work.

We thank the community for their patience during the delivery of this important project.

 

Current Works (last updated 24/10/25) Latest information in bold:

Community Centre Building:

  • Installation of internal gyprock to walls and ceilings
  • Roofing work, including gutting and fascia
  • Landscaping works in youth playground
  • Commencement of concrete work.
Anthony Skarratt Reserve Nelson Road, Box Hill – Progress photo of Community Centre Building, Carpark and Playground Stage 1.jpg

Anthony Skarratt Reserve Nelson Road, Box Hill – Progress photo of Community Centre Building and Carpark.

Anthony Skarratt Reserve Nelson Road Box Hill – Progress photo of Community Centre Building, Carpark and Playground (Stage 1).jpg

Anthony Skarratt Reserve Nelson Road Box Hill – Progress photo of Community Centre Building, Carpark and Playground (Stage 1).

Anthony Skarratt Plan (Nov 2023).PNG

 

Omniwarrior Course & Bouldering Wall

Omniwarrior Course & Bouldering Wall

Outdoor Gym

Outdoor Gym

 

Location

8 Nelson Road, Box Hill 2765  View Map

Google Map