Renown Road Bridge Upgrade Works
Upgrade Works Renown Rd Bridge over Darling Mills Creek, Baulkham Hills
The Hills Shire Council is committed to manage and maintain assets and infrastructure under Council’s control to meet the needs of our community and future generations.
The goals of the project are:
Renown Rd Bridge over darling Mills Creek, Baulkham Hills was identified in the capital works programme 2009-2010 to improve the safety of the bridge and road, including widening of bridge and road including break down bays to both travelling lanes and installation of concrete median barrier. The budget estimate for the whole of the works determined the requirement to deliver the project in stages. The first stage of the works will deliver the provision of breakdown bays and associated works, providing emergency facilities improving the safety for the community and motorists.
The work included for works comprises the following major activities:
- Widening of carriageway including construction of breakdown bays and associated works;
- Bridge deck widening to accomodate central concrete median barrier;
- Construction of retaining wall, southern break down bay;
- Stormwater upgrade works;
- Relocation of street lights
- Installation of guard rails;
- Pedestrian bolt on steel deck, including floor panel and pedestrian fencing;
- Pedestrian fencing
Contract Information
Stage 1 contract awarded to Nicolson Earthworks Pty Ltd
Stage 2 contract awarded to Delaney Civil Pty Ltd
Civil contract works completed July 2012
Downloads and Updates
Renown Rd Bridge drawings:
General Arrangement Plan and Longsection (725.75kB)
Typical Sections and Details (244.89kB)
Pavement Plan, Kerb and Barrier Details (329.91kB)
View the Renown Road Bridge Upgrade Works Construction Photo Gallery
Contact Information
lf you would like more information about this project or if you would like to provide us with your feedback, contact Martin Lacher - Phone: 02 - 9843 0349 or Email: mlacher@thehills.nsw.gov.au
Please be advised that the information provided on this website is subject to change.
M2 Contact details
Council appreciates your direct contact with the M2 community officer in relation to the lane changes, traffic disruption or duration of project works by contacting the hotline on 1800 196 266 or visit http://www.hillsm2upgrade.com.au/project.htm
M2 Upgrade Project Barclay Rd Traffic Management Plan (263.72kB)
Back to Top